Petrochemical

We have a lot of experience of working with clients in the petrochemical sector, find out more below.

Project: Basell Polyolefins
Client: Basell Polyolefins
Value: £1m
Duration: 10 Weeks

Lyondell Basell is one of the world’s largest plastic, chemical and refining companies and is the largest producer of polypropylene and polypropylene compounds in the world.

Scope of works

To dismantle all redundant steelwork and pipework from the Carrington site that has been identified for disposal and replacement with new.

Key considerations

To ensure the smooth transition from redundant to replacement steel and pipework, the PP O’Connor team worked to a demanding timetable to ensure minimum disruption was caused to the productivity of the plant.

 

Project:Shell, Stanlow
Client: Shell
Duration: 15 Years

PP O’Connor has been working with the team at Shell Stanlow for over 15 years.

Scope of works

Decommissioning and deconstruction of redundant buildings, excavation of concrete slabs, and on site crushing of materials for re-use on site.

Project innovation

PP O’Connor was the first company to crush materials on site at this facility. This has resulted in 99% of materials being crushed in situ for re-use within the site, contributing considerably to the facilities carbon footprint.